m[i].l=1*new Date(); for (var j = 0; j < document.scripts.length; j++) {if (document.scripts[j].src === r) { return; }} k=e.createElement(t),a=e.getElementsByTagName(t)[0],k.async=1,k.src=r,a.parentNode.insertBefore(k,a)}) (window, document, "script", "https://mc.yandex.ru/metrika/tag.js", "ym"); ym(95911708, "init", { clickmap:true, trackLinks:true, accurateTrackBounce:true });
ruseng

Information on the progress of construction of CASA-1000 in Kyrgyzstan

19 апреля 2022
Views: 384

As part of the implementation of the CASA-1000 project in Kyrgyzstan, the construction of a 500 kV transmission line is underway.

In total, 455.6 kilometers of transmission lines will be laid in Kyrgyzstan from a 500 kV cell, which will be built specifically for this transmission line at the 500 kV Datka substation, from which the line will stretch through Jalal-Abad, Osh and Batken regions to the border with Tajikistan.

To date, the following construction works have been completed:

The construction of access roads to the construction sites of supports was completed for 955 supports (76%), digging pits for supports - 897 (72%), reinforcement and pouring of concrete - 742 (59%), installation of supports - 436 (35%). A total of 1241 supports will be built under the project.

Currently, active work is being carried out in Batken, Osh and Jalal-Abad regions. The work involves 84 units of special equipment and special vehicles, 44 units of vehicles and 230 workers, of which about 70% are local residents.

To mobilize specialists for the construction of infrastructure facilities in these three regions, 6 construction bases have been created.

Reference: CASA-1000 is designed to connect the energy systems of Central Asia with South Asia - Kyrgyzstan, Tajikistan with Afghanistan and Pakistan and develop mechanisms for electricity trade in accordance with international standards.