m[i].l=1*new Date(); for (var j = 0; j < document.scripts.length; j++) {if (document.scripts[j].src === r) { return; }} k=e.createElement(t),a=e.getElementsByTagName(t)[0],k.async=1,k.src=r,a.parentNode.insertBefore(k,a)}) (window, document, "script", "https://mc.yandex.ru/metrika/tag.js", "ym"); ym(95911708, "init", { clickmap:true, trackLinks:true, accurateTrackBounce:true });
ruseng

Information on the progress of construction of CASA-1000 in Kyrgyzstan

02 августа 2023
Views: 167

As part of the CASA-1000 project in Kyrgyzstan, construction work continues on a 500 kV power line and a 500 kV cell at the Datka substation.

To date, work has been completed on laying access roads to the towers (100%), digging pits (100%) and pouring concrete foundations (100%) of all 1243 towers. Work is underway on the installation of poles, where 1236 poles (99%) have already been installed and wires have been installed at 265.78 km (58%).

Major construction and installation works have been successfully completed at the Datka substation. In particular, a 500 kV shunt reactor with accessories, a neutral, an oil pit and fire barriers, 3 sets of 500 kV automatic switches, 3 sets of 500 kV current transformers, 6 500 kV lightning rods and other equipment were installed, as well as power and control cables with a total length over 475 meters.

Reference: CASA-1000 is designed to connect the energy systems of Central Asia with South Asia - Kyrgyzstan, Tajikistan with Afghanistan and Pakistan. This will enable the development of electricity trading mechanisms in accordance with international standards

Add comment

Name: *

Email:

Text: *